Refurbishment, Hockley, Birmingham

Refurbishment to the Old Kettle Works, Hockley.

The old roof panels where removed.  My team was required to fit the brackets, fix the METSEC Roof Joists and 18mm Ply, ready for the roofers to apply the new roof.
 


Click on the thumbnail to enlarge.
  • Infill 'Before' photo.
    SFS infill, on a Colmore Tang site, Hockley, Birmingham.

Subcontracting to CPL.
    SFS infill, on a Colmore Tang site, Hockley, Birmingham.

    Subcontracting to CPL.

  • Image of Roof Joists, Hockley.
    6mm Galvanised Brackets used as fixing points for the 150mm METSEC Roof Joists.  

The steel was pre drilled with a Magdrill. M8 bolts through the brackets on to the steel.
    6mm Galvanised Brackets used as fixing points for the 150mm METSEC Roof Joists.

    The steel was pre drilled with a Magdrill. M8 bolts through the brackets on to the steel.

  • Infill Finish 'After' Photo
    Image taken underneath the METSEC infill. showing the METSEC Roof Joists and the 18mm 'treated' Plywood.  Ready for the Roofers to apply the new roof.
    Image taken underneath the METSEC infill. showing the METSEC Roof Joists and the 18mm 'treated' Plywood. Ready for the Roofers to apply the new roof.